Railway electrification Completed
During the last couple of years our company has provided following services in railway electrification activity. The details of completed services is as under
- Western Railway
- Central Railway
- South Eastern Railway
- CORE, Prayagraj
- Southern Railway
- RVNL
- BHEL
- East Cost Railway
Udhana - Jalgaon Section
Work Description :
Design, fabrication, Supply, Erection, Testing & Commissioning of 25KV single phase AC traction OHE in connection with Phase-II work of doubling of Udhana - Jalgaon section of Mumbai Division of Western Railway. Mumbai Division of Western Railway. WA-6
Project Value :
Rs. 1204.37 Lakhs
Total TKM :
100.37 TKM
Project Duration :
12 Months
Nardana -Amalner Section
Work Description :
Design, fabrication, Supply, Erection, Testing & Commissioning of 25KV single phase AC traction OHE in connection with balance work of OHE in Nardana -Amalner Section of UDN-JL work of doubling of Udhana - Jalgaon section of Mumbai Division of Western Railway. (Nardana -Amalner Section) WA-9
Project Value :
Rs. 992.86 Lakhs
Total TKM :
40.00 TKM
Project Duration :
6 Months
Nandurbar - Dondaicha Section
Work Description :
Design, fabrication, Supply, Erection, Testing & Commissioning of 25KV single phase AC traction OHE in connection with balance work of OHE in Nandurbar - Dondaicha (including ) & other leftover work in Section of UDN-JL work of doubling of Udhana - Jalgaon section of Mumbai Division of Western Railway. (Nandurbar - Dondaicha Section) WA-10
Project Value :
Rs. 2576.93 Lakhs
Total TKM :
85.00 TKM
Project Duration :
9 Months
Churchgate - Virar Section
Work Description :
Replacement of corroded OHE structures by GI OHE structures between Church gate - Virar Section
Project Value :
Rs. 290.82 Lakhs
Project Duration :
12 Months
Mahesana - Taranghill Section
Work Description :
Design, fabrication, Supply, Erection, Testing & Commissioning of 25KV, AC OHE between Mahesana-Taranghill Section on Ahemdabad Division of Western Railway. (Mahesana-Taranghill Section)
Project Value :
Rs. 2046.70 Lakhs
Total TKM :
65 TKM
Project Duration :
6 Months
Ujjain - Fatihabad Section
Work Description :
Design, fabrication, Supply, Erection, Testing & Commissioning of 25KV, AC OHE between UJN-FTD Section on Ratlam Division of Western Railway (Ujjain-Fatihabad Section)
Project Value :
Rs. 1207.84 Lakhs
Total TKM :
32 TKM
Project Duration :
6 Months
Boriyavi to Vadtal Section
Work Description :
Design, Supply, Erection, Testing & Commissioning of 25 KV AC OHE between Anand to Khambhat with Boriyavi to Vadtal Section
Project Value :
Rs. 1759.37 Lakhs
Total TKM :
55 TKM
Project Duration :
6 Months
Mumbai Division
Work Description :
Conversion of 1500V DC OHE to 25000 V AC OHE Inclusive of design supply erection, testing, and commissioning, of 25KV ac single phase 50 Hz, tracation ovearhead equipment in varous yard of Mumbai Division of Central Railway
Project Value :
Rs. 1544.67 Lakhs
Total TKM :
50 TKM
Project Duration :
18 Months
Kalyan - Vangani Section
Work Description :
Replacement of OHE steel structures between Kalyan - Vangani Section
Project Value :
Rs. 269.67 Lakhs
Total TKM :
48 TKM
Project Duration :
12 Months
Work Description :
Design, Supply, Erection, Testing & Commissioning of Diesel Generator set of various capacities, 11 KV/415V, 3 Phase power distribution transformers, HT & LT Switchgears including construction of DG set rooms in connection with off loading of 2.2KV traction
Project Value :
Rs. 445.49 Lakhs
Project Duration :
12 Months
Work Description :
Replacement of 600 Amp rated Rocker type Isolator by 1250 Amp rated Knife type Isolator.
Project Value :
Rs. 248.36 Lakhs
Project Duration :
6 Months
Kharagpur Division
Work Description :
Renewal of overhead equipment over khargapur Division
Project Value :
Rs. 625.78 Lakhs
Total TKM :
70
Project Duration :
15 Months
Jammu Tawi - Udhampur Section
Work Description :
Provision of fixtures for erection of OHE in tunnels in the existing tunnels of various lengths, ( from 60 m to 2444m)" in Jummu Tawi (Excl)- Udhampur (incl) section of Firozpur Division (Jummu Tawi - Udhampur Section) ( Gr.143)
Project Value :
Rs. 190.00 Lakhs
Project Duration :
3 Months
Coimbatore North - Mettupalayam Section
Work Description :
Design, Supply, Erection, Testing & Commissioning of 25 kV, 50 Hz, AC, Single Phase Over Head Equipments, Switching Stations in Coimbatore North (Excl.) – Mettupalayam (Incl.) Section, Southern Railway under RE Project Chennai (Coimbatore North - Mettupalayam Section) (Gr.-169)
Project Value :
Rs. 790.14 Lakhs
Total TKM :
39.50 TKM
Project Duration :
9 Months
Settihalli-Yeliyur
Work Description :
Design, Supply, Erection, Testing & Commissioning of 25 kV, 50 Hz, AC, Single Phase, Traction Overhead Equipments, Switching Stations in settihalli - yeliyur double line section in of South Western Railway
Project Value :
Rs. 1442.36 Lakhs
Total TKM :
90 TKM
Project Duration :
15 Months
YELIYUR - MYSORE
Work Description :
Design, Supply, Erection, Testing & Commissioning of 25 kV, 50 Hz, AC, Single Phase, Traction Overhead Equipment’s, Switching Stations in YELIYUR - MYSORE DOUBLE LINE SECTION of South Western Railway. (Gr.156)
Project Value :
Rs. 1585.56 Lakhs
Total TKM :
101
Project Duration :
15 Months
ENRICH-TRIMURTHI (JV)
Tiruchchirappalli Division
Work Description :
Design, Supply, Erection, Testing & Commissioning of 25 kV, 50 Hz, Single Phase, AC, Electrification Works including OHE & TSS as Composite Electrical Work" for balance work in Thanjavur Jn.(Excl.)-ThiruvarurJn,(Incl.)- Karaikal and Nagappatinam-Velankanni Section, Group-210 in Tiruchchirappalli Division of Southern Railway under RE Project Chennai, Total 105 RKM/ 125 TKM.
Project Value :
Rs. 2940.86 Lakhs
Total TKM :
125 TKM
Project Duration :
12 Months
Salem Division
Work Description :
Tiruppattur - Karuppur - Replacement of MCI Fittings in Cantilever Assembly (Cantilever Assembly 250 Nos. Cantilever Fittings 2000 Nos.) of 25 kv Overhead Equipment (OHE) in Salem Division - Reg. Southern Railway.
Project Value :
Rs. 3.25 Lakhs
Project Duration :
6 Months
Jhansi Division
Work Description :
Design, Supply, Erection, testing and commissioning of 25KV, 50Hz, single phase overhead equipment with modification to existing OHE and General Electrical works of ORAI YARD in connection with doubling between Jhansi and Bhimsen station on Jhansi Division of North Central Railway in the state of Uttar Pradesh, India.
Project Value :
Rs. 364.48 Lakhs
Project Duration :
6 Months
ENRICH-PRFW (JV)
Section “Bhandai to Urimore”
Work Description :
Overhead Equipment” Supply and works tender for section “Bhandai to Urimore” for Railway Electrification Birlanagar-Etawah 386RKM/440TKM project”
Project Value :
Rs. 2146.79 Lakhs
Total TKM :
440 TKM
Project Duration :
12 Months
Inland Engineers-ENRICH (JV)
Khurda Division
Work Description :
Design, supply, erection, testing and commissioning of 25kV OHE from Salegaon to Rajathgarh section including modification in yards and Kapilas Road to Nergundi section including modification in yards in connection with 3rd & 4th line between Salegaon-Budhapank and 3rd line between Bhadrak-Nergundi in Khurda Division of East Coast Railway.
Project Value :
Rs. 2735.18 Lakhs
Total TKM :
84 TKM
Project Duration :
18 Months