Railway electrification Completed

During the last couple of years our company has provided following services in railway electrification activity. The details of completed services is as under

Udhana - Jalgaon Section

Work Description :

25KV single phase AC traction OHE in connection with Phase-II work of doubling of Mumbai Division.

Total TKM :

100.37 TKM

Project Duration :

12 Months

Nardana -Amalner Section

Work Description :

25KV single phase AC traction OHE in connection with balance work of OHE in Nardana -Amalner Section.

Total TKM :

40.00 TKM

Project Duration :

6 Months

Nandurbar - Dondaicha Section

Work Description :

25KV single phase AC traction OHE in connection with balance work of OHE.

Total TKM :

85.00 TKM

Project Duration :

9 Months

Churchgate - Virar Section

Work Description :

Replacement of corroded OHE structures by GI OHE structures between Church gate - Virar Section

Project Duration :

12 Months

Mahesana - Taranghill Section

Work Description :

25KV, AC OHE between Mahesana-Taranghill Section on Ahemdabad Division.

Total TKM :

65 TKM

Project Duration :

6 Months

Ujjain - Fatihabad Section

Work Description :

25KV, AC OHE between UJN-FTD Section on Ratlam Division.

Total TKM :

32 TKM

Project Duration :

6 Months

Boriyavi to Vadtal Section

Work Description :

Design, Supply, Erection, Testing & Commissioning of 25 KV AC OHE work.

Total TKM :

55 TKM

Project Duration :

6 Months

Nardana -Amalner Section

Work Description :

25KV single phase AC traction OHE in connection with balance work of OHE

Total TKM :

WA-9- 40 TKM

Project Duration :

16 Month

Mumbai Division

Work Description :

Railway OHE electrification work of line No. 8 & 9 at NDB yard in UDN-JL section

Total TKM :

Project Duration :

39 Months

Ratlam Division

Work Description :

Railway electrification work in Nimbahera - Nimach Section on Ratlam Division of Western Railway in connection with Doubling project between Chittorgarh – Nimach

Total TKM :

45 TKM.

Project Duration :

21 Months

Mysuru Division

Work Description :

25KV OHE works Raw Hassan -Arsikere in Mysuru Division, South-Western Railway, Karnataka, India.

Total TKM :

52 TKM

Project Duration :

12 Months

Churchgate - Virar Section

Work Description :

Churchgate - Virar Section Replacement of corroded OHE Structures 622

Total TKM :

35 TKM

Project Duration :

12 Months

Nimbahera - Nimach Section

Work Description :

25 KV AC OHE including removal of infringements between Nimbahera - Nimach Section on Doubling project between Chittorgarh - Nimach.

Total TKM :

38 TKM

Project Duration :

15 Months

Thane - Diva Division

Work Description :

Mumbai for provision of 5th & 6th line between Thane-Diva Stations of Central Railway of (MUTP-II)

Total TKM :

32.86 TKM

Project Duration :

24 Months

Raipur Division

Work Description :

Marauda - Dallirajhara section, Group-355 in Raipur Division of South-East Central Railway under RE Project Lucknow,

Total TKM :

120 TKM.

Project Duration :

12 Months

Kharagpur Division

Work Description :

OHE work - Rupsa - Bangriposi section of Kharagpur Division of South-Eastern Railway under RE Project Bhubaneswar

Total TKM :

96 TKM

Project Duration :

12 Months

Adra Division

Work Description :

Railway electrification of unwired loop lines and yard lines of Adra Division over S.E.Railway Uner Juridiction of ADEE/TRD/ADA.

Total TKM :

Project Duration :

18 Months

V-Bro Engineers (JV)

Work Description :

Electrification of unwired loop lines and yard lines of Adra Division over S.E.Railway Uner Juridiction of ADEE/TRD/ADA.

Total TKM :

33 TKM

Project Duration :

18 Months

ENRICH-SKE (JV) Kharagpur division

Work Description :

25KV OHE including RC and PSI work from NYA to BLDA and modification of JER/YD, RGT/YD & ROP/YD in connection with the work of 3rd line between Narayangarh (Ex.) and Bhadrak

Total TKM :

42 TKM

Project Duration :

18 Months

Jammu Tawi - Udhampur Section

Work Description :

Provision of fixtures for erection of OHE in tunnels in the existing tunnels of various lengths, ( from 60 m to 2444m)" in Jummu Tawi (Excl)- Udhampur (incl) section of Firozpur Division (Jummu Tawi - Udhampur Section) ( Gr.143)

Project Duration :

3 Months

Coimbatore North - Mettupalayam Section

Work Description :

25 kV, 50 Hz, AC, Single Phase Over Head Equipments, Switching Stations in Coimbatore North.

Total TKM :

39.50 TKM

Project Duration :

9 Months

Settihalli-Yeliyur

Work Description :

25 kV, 50 Hz, AC, Single Phase, Traction Overhead Equipments, Switching Stations.

Total TKM :

90 TKM

Project Duration :

15 Months

YELIYUR - MYSORE

Work Description :

25 kV, 50 Hz, AC, Single Phase, Traction Overhead Equipment’s, Switching Stations in YELIYUR - MYSORE DOUBLE LINE SECTION of South Western Railway.

Total TKM :

101

Project Duration :

15 Months

ENRICH-TRIMURTHI (JV)

Tiruchchirappalli Division

Work Description :

25 kV, 50 Hz, Single Phase, AC, Electrification Works including OHE & TSS as Composite Electrical Work" for balance work in Thanjavur Jn.(Excl.)-ThiruvarurJn,(Incl.)- Karaikal and Nagappatinam-Velankanni Section.

Total TKM :

125 TKM

Project Duration :

12 Months

ENRICH-SWPL (JV) Marauda - Dallirajhara section

Work Description :

25 kV, 50 Hz, Single Phase, AC, Electrification Works including OHE & TSS as Composite Electrical Work" for Marauda - Dallirajhara section, Group- 355.

Total TKM :

120 TKM

Project Duration :

12 Months

ENRICH-SWPL (JV) Sahaspur-Sambhal Hatim section

Work Description :

25 kV, 50 Hz, Single Phase, AC, Electrification Works including OHE & TSS as Composite Electrical Work" for Sonipat -Gohana-Jind.

Total TKM :

126 TKM

Project Duration :

12 Months

ENRICH-SWPL (JV) Yelahanka (Excl.) - Bangarpet (Excl.) Section

Work Description :

OHE & TSS as Composite Electrical Work" in Yelahanka (Excl.) - Bangarpet (Excl.) Section Gr.294 of Bangaluru division

Total TKM :

170 TKM

Project Duration :

12 Months

Inland Engineers-ENRICH (JV) Sambalpur Division

Work Description :

OHE work 25 kV, 50 Hz, Single Phase, AC, Electrification including OHE& TSS as Composite Electrical Work.

Total TKM :

125 TKM

Project Duration :

12 Months

Inland Engineers-ENRICH (JV) Rupsa - Bangriposi section

Work Description :

25 kV, 50 Hz, Single Phase, AC Electrification including OHE& TSS as Composite Electrical Work"

Total TKM :

96 TKM

Project Duration :

12 Months

Firozpur division

Work Description :

Single Phase 25 KV AC OHE regarding TRD work in c/w "Electrification of ACTL Siding at Samba (SMBX)

Project Duration :

6 Months

Chennai Division

Work Description :

OHE work at Tambaram (TBM) and Guduvancheri (GI) stations in connection with laying of 3rd line between Tambaram – Chengalpattu section

Total TKM :

16.036 TKM

Project Duration :

10 Months

Bengaluru division

Work Description :

Yelahanka (Excl.) - Bangarpet (Excl.) Section Gr.294 of Bangaluru division of South-Western Railway

Total TKM :

170 TKM

Project Duration :

12 Months

Tambaram - Chengalpattu Section

Work Description :

OHE Electrification works on the 3rd line between Tambaram (TBM) and Guduvancheri (GI) stations in connection with laying of 3rd line between Tambaram – Chengalpattu section

Total TKM :

12 TKM

Project Duration :

10 Months

Salem Division

Work Description :

Tiruppattur - Karuppur - Replacement of MCI Fittings in Cantilever Assembly (Cantilever Assembly 250 Nos. Cantilever Fittings 2000 Nos.) of 25 kv Overhead Equipment (OHE) in Salem Division - Reg. Southern Railway.

Total TKM :

Project Duration :

6 Months

Jhansi Division

Work Description :

25KV, 50Hz, single phase overhead equipment with modification to existing OHE and General Electrical works in ORAI YARD.

Project Duration :

6 Months

ENRICH-PRFW (JV)

Section “Bhandai to Urimore”

Work Description :

Overhead Equipment” Supply and works tender for section “Bhandai to Urimore” for Railway Electrification Birlanagar-Etawah 386RKM/440TKM project”

Total TKM :

440 TKM

Project Duration :

12 Months

Bhadrak in Kharagpur division

Work Description :

25KV OHE including RC and PSI work from NYA to BLDA and modification of JER/YD, RGT/YD & ROP/YD in connection with the work of 3rd line between Narayangarh (Ex.) and Bhadrak.

Total TKM :

42 TKM

Project Duration :

12 Months

Samastipur Division

Work Description :

25KV OHE and PSI works between Banmankhi (Incl.) - Bihariganj (lncl.) in connection with Gauge Conversion of the section

Total TKM :

32 TKM

Project Duration :

8 Months

Sambalpur Division

Work Description :

Railway electrification work Nuagaon and Balangir - Bhainsapalli section, Gr. 348 .

Total TKM :

125 TKM

Project Duration :

18 Months

Jhansi Division

Work Description :

ORAI YARD in connection with doubling between Jhansi and Bhimsen station

Total TKM :

Project Duration :

6 Months

Prayagraj Division

Work Description :

25 KV 50 HZ, AC OHE of 4th line of Chipiyana Buzurg - Dadri section of Prayagraj Division of N.C. Railway.

Total TKM :

20 TKM

Project Duration :

12 Months

Ambala & Moradabad Division

Work Description :

Sonipat -Gohana-Jind and Raja Ka Sahaspur-Sambhal Hatim section, Group-285 & 286 in Ambala & Moradabad Division

Total TKM :

126 TKM

Project Duration :

12 Months

Firozpur division

Work Description :

Single Phase 25 KV AC OHE regarding TRD work in c/w "Electrification of ACTL Siding at Samba (SMBX)

Total TKM :

Project Duration :

6 Months