Project Value: Rs. 269.67 Lacs. Total TKM:  48 TKM Project Duration: 12 Months Work Description:  Replacement of OHE steel structures between Kalyan – Vangani Section

Central Railway

Project Value: Rs. 445.49 Lacs. Total TKM:  NA TKM Project Duration: 12 Months Work Description:  Design, Supply, Erection, Testing & Commissioning of Diesel Generator set of various capacities, 11 KV/415V, 3 Phase power distribution transformers, HT & LT Switchgears including construction of DG set rooms in connection with off loading of 2.2KV traction

Central Railway

Project Value: Rs. 15,44,67,599 Lacs. Total TKM: 50 TKM Project Duration: 18 months Work Description:  Conversion of 1500V DC OHE to 25000 V AC OHE Inclusive of design supply erection, testing, and commissioning, of 25KV ac single phase 50 Hz, tracation ovearhead equipment in varous yard of Mumbai Division of Central Railway