Project Value: 17,40,86,805/- Total TKM:  65 TKM Project Duration:  13 Months Work Description:  Design, fabrication, Supply, Erection, Testing & Commissioning of 25KV, AC OHE between Mahesana-Taranghill Section on Ahemdabad Division of Western Railway. (Mahesana-Taranghill Section)

Western Railway

Project Value: 10,90,82,070/- Total TKM:  32 TKM Project Duration:  8 Months Work Description:  Design, fabrication, Supply, Erection, Testing & Commissioning of 25KV, AC OHE between UJN-FTD Section on Ratlam Division of Western Railway (Ujjain-Fatihabad Section)

Western Railway

Project Value: 3,41,17,605/- Total TKM:  35 TKM Project Duration: 11 Months Work Description:  Replacement of corroded OHE Structures between Churchgate -Virar Section

Western Railway

Project Value: 4,87,22,287/- Total TKM:  50 TKM Project Duration: 11 Months Work Description:  Replacement of corroded OHE Structures between Churchgate -Virar Section

Western Railway

Project Value: 31,03,15,195/- Total TKM:  60 TKM Project Duration: 24 Months Work Description:  Design, fabrication, Supply, Erection, Testing & Commissioning of 25KV, AC OHE between BCT-BVI Section on Mumbai Division of Western Railway in connections with 6th Line Work. (Mumbai Central-Borivali Section)